Park Lane. Water main replacement
Milling and paving on Park and Gladish were completed
Work to be performed the week of November 5 to November 9.
Finish Driveway installations weather permitting
Finish Landscaping weather permitting
Final water main tie in at the south end of the park
The project is nearing completion. We still have a few things to complete. I would most sincerely like to thank you once again for your cooperation and patience throughout this project.
Friday, November 2, 2018
Monday, October 29, 2018
Park Ave. Water main replacement
Work completed this week.
Water main was completed through the park area.
Work to be performed the week of October October 29 to November 2.
Milling and paving on Park Ave.
Punch list items
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patienc
Work completed this week.
Water main was completed through the park area.
Work to be performed the week of October October 29 to November 2.
Milling and paving on Park Ave.
Punch list items
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patienc
Thursday, October 11, 2018
Park Ave. Water main replacement
Work completed this week.
Gladish s. of Park was paved with Binder
Landscaping continuing on Park and Gladish
Work to be performed the week of October 15th to October 19th.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience.
Work completed this week.
Gladish s. of Park was paved with Binder
Landscaping continuing on Park and Gladish
Work to be performed the week of October 15th to October 19th.
- Landscaping Tentatively scheduled for middle of next week on Park and Gladish
- Water main through the park is tentative to begin on Monday weather permitting
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience.
Friday, October 5, 2018
Park Ave. Water main replacement
Work completed this week.
Trench patching was completed on Park Ave.
Gladish s. of Park was milled and prepped for paving
Was to be paved today Friday, but do to the weather paving was cancelled for Today. Tentatively set for Saturday October 6 or Monday October 8th
Work to be performed the week of October 8th to October 12th.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience
Work completed this week.
Trench patching was completed on Park Ave.
Gladish s. of Park was milled and prepped for paving
Was to be paved today Friday, but do to the weather paving was cancelled for Today. Tentatively set for Saturday October 6 or Monday October 8th
Work to be performed the week of October 8th to October 12th.
- Park Ln is tentatively scheduled to be milled and asphalt binder installed
- Landscaping Tentatively scheduled for middle of next week on Park and Gladish
- Water main through the park is tentative for next week to begin
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience
Friday, September 21, 2018
Park Ave. Water main replacement Stage I
Stage I consists of the water main replacement and pavement repairs.
Work to be performed the week of September 24th, to September 28th.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience
Stage I consists of the water main replacement and pavement repairs.
Work to be performed the week of September 24th, to September 28th.
- Finished storm sewers this week
- Finish pouring curbs and drives early next week.
- Tentatively mill, patch and pave binder on Park Ave..
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience
Saturday, September 15, 2018
Park Ave. Water main replacement Stage I
Stage I consists of the water main replacement and pavement repairs.
Work to be performed the week of September 17th, to September 21st.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience
Stage I consists of the water main replacement and pavement repairs.
Work to be performed the week of September 17th, to September 21st.
- Complete storm sewer work
- begin prepping for curb remove and replace.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience
Sunday, September 9, 2018
Park Ave. Water main replacement Stage I
Stage I consists of the water main replacement.
Work completed last week.
Work to be performed the week of September 10th, to September 14th,
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads.
I would most sincerely like to thank you in advance for your cooperation and patience.
Stage I consists of the water main replacement.
Work completed last week.
Work to be performed the week of September 10th, to September 14th,
- Start phase 2 water main
- Start installation of Storm sewer.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads.
I would most sincerely like to thank you in advance for your cooperation and patience.
Friday, August 24, 2018
Park Ave. Water main replacement Stage I
Stage I consists of the water main replacement.
Work completed last week.
Work to be performed the week of August 27th, to August 31st.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads.
I would most sincerely like to thank you in advance for your cooperation and patience.
Stage I consists of the water main replacement.
Work completed last week.
Work to be performed the week of August 27th, to August 31st.
- Tentatively finish the water main and begin chlorination and testing process.
- Start installation of Storm sewer.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads.
I would most sincerely like to thank you in advance for your cooperation and patience.
Friday, August 17, 2018
Park Ave. Water main replacement Stage I
Stage I consists of the water main replacement.
Work completed last week.
Work to be performed the week of August 20th, to August 24th.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads.
I would most sincerely like to thank you in advance for your cooperation and patience.
Stage I consists of the water main replacement.
Work completed last week.
Work to be performed the week of August 20th, to August 24th.
- Continuing with the installation of water main and sanitary sewer
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads.
I would most sincerely like to thank you in advance for your cooperation and patience.
Friday, August 10, 2018
Park Ave. Water main replacement Stage I
Stage I consists of the water main replacement.
Work to be performed the week of August 13th, to August 17th.
- Starting Monday the contractor will begin saw cutting for pavement removal and water main replacement.
Construction will be in full swing next week.
I would like to thank you in advance for your cooperation and patience.