Park Ave. Water main replacement Stage I

Stage I consists of the water main replacement.

Work completed last week.


Work to be performed the week of  September 10th, to September 14th,

  • Start phase 2 water main 
  • Start installation of Storm sewer.


As I'm sure we can all  agree the area is pretty congested with the construction work and narrow roads.
I would most sincerely like to thank you in advance for your cooperation and patience.