Park Ave. Water main replacement
Work completed this week.
Water main was completed through the park area.
Work to be performed the week of October October 29 to November 2.
Milling and paving on Park Ave.
Punch list items
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patienc
Monday, October 29, 2018
Thursday, October 11, 2018
Park Ave. Water main replacement
Work completed this week.
Gladish s. of Park was paved with Binder
Landscaping continuing on Park and Gladish
Work to be performed the week of October 15th to October 19th.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience.
Work completed this week.
Gladish s. of Park was paved with Binder
Landscaping continuing on Park and Gladish
Work to be performed the week of October 15th to October 19th.
- Landscaping Tentatively scheduled for middle of next week on Park and Gladish
- Water main through the park is tentative to begin on Monday weather permitting
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience.
Friday, October 5, 2018
Park Ave. Water main replacement
Work completed this week.
Trench patching was completed on Park Ave.
Gladish s. of Park was milled and prepped for paving
Was to be paved today Friday, but do to the weather paving was cancelled for Today. Tentatively set for Saturday October 6 or Monday October 8th
Work to be performed the week of October 8th to October 12th.
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience
Work completed this week.
Trench patching was completed on Park Ave.
Gladish s. of Park was milled and prepped for paving
Was to be paved today Friday, but do to the weather paving was cancelled for Today. Tentatively set for Saturday October 6 or Monday October 8th
Work to be performed the week of October 8th to October 12th.
- Park Ln is tentatively scheduled to be milled and asphalt binder installed
- Landscaping Tentatively scheduled for middle of next week on Park and Gladish
- Water main through the park is tentative for next week to begin
As I'm sure we can all agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience
Subscribe to:
Posts (Atom)