Park Ave. Water main replacement

Work completed this week.

Gladish s. of Park was paved with Binder
Landscaping continuing on Park and Gladish



Work to be performed the week of  October 15th to October 19th.


  • Landscaping Tentatively scheduled for middle of next week on Park and Gladish
  • Water main through the park is tentative to begin on Monday weather permitting