Friday, November 2, 2018

Park Lane. Water main replacement

Milling and paving on Park  and Gladish were completed



Work to be performed the week of November 5 to November 9.

Finish Driveway installations weather permitting
Finish Landscaping weather permitting
Final water main tie in at the south end of the park


The project is nearing completion. We still have a few things to complete. I would most sincerely like to thank you once again for your cooperation and patience throughout this project.

Monday, October 29, 2018

Park Ave. Water main replacement

Work completed this week.

Water main was completed through the park area.



Work to be performed the week of  October October 29 to November 2.

Milling and paving on Park Ave.
Punch list items


As I'm sure we can all  agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patienc

Thursday, October 11, 2018

Park Ave. Water main replacement

Work completed this week.

Gladish s. of Park was paved with Binder
Landscaping continuing on Park and Gladish



Work to be performed the week of  October 15th to October 19th.


  • Landscaping Tentatively scheduled for middle of next week on Park and Gladish
  • Water main through the park is tentative to begin on Monday weather permitting


As I'm sure we can all  agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience.

Friday, October 5, 2018

Park Ave. Water main replacement

Work completed this week.

Trench patching was completed on Park Ave.
Gladish s. of Park was milled and prepped for paving
Was to be paved today Friday, but do to the weather paving was cancelled for Today. Tentatively set for Saturday October 6 or Monday October 8th


Work to be performed the week of  October 8th to October 12th.

  • Park Ln is tentatively scheduled to be milled and asphalt binder installed
  • Landscaping Tentatively scheduled for middle of next week on Park and Gladish
  • Water main through the park is tentative for next week to begin


As I'm sure we can all  agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience

Friday, September 21, 2018

Park Ave. Water main replacement Stage I

Stage I consists of the water main replacement and pavement repairs.


Work to be performed the week of  September 24th, to September 28th.

  • Finished storm sewers this week
  • Finish pouring curbs and drives early next week.
  • Tentatively mill, patch and pave binder on Park Ave..


As I'm sure we can all  agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience

Saturday, September 15, 2018

Park Ave. Water main replacement Stage I

Stage I consists of the water main replacement and pavement repairs.


Work to be performed the week of  September 17th, to September 21st.

  • Complete storm sewer work
  • begin prepping for curb remove and replace.


As I'm sure we can all  agree the area is pretty congested with the construction work and narrow roads. I would most sincerely like to thank you in advance for your cooperation and patience

Sunday, September 9, 2018

Park Ave. Water main replacement Stage I

Stage I consists of the water main replacement.

Work completed last week.


Work to be performed the week of  September 10th, to September 14th,

  • Start phase 2 water main 
  • Start installation of Storm sewer.


As I'm sure we can all  agree the area is pretty congested with the construction work and narrow roads.
I would most sincerely like to thank you in advance for your cooperation and patience.