Friday, November 2, 2018

Park Lane. Water main replacement

Milling and paving on Park  and Gladish were completed



Work to be performed the week of November 5 to November 9.

Finish Driveway installations weather permitting
Finish Landscaping weather permitting
Final water main tie in at the south end of the park


The project is nearing completion. We still have a few things to complete. I would most sincerely like to thank you once again for your cooperation and patience throughout this project.