Park Ave. Water main replacement Stage I

Stage I consists of the water main replacement.

Work completed last week.


Work to be performed the week of August 27th, to August 31st.

  • Tentatively finish the water main and begin chlorination and testing process.
  • Start installation of Storm sewer.


As I'm sure we can all  agree the area is pretty congested with the construction work and narrow roads.